Home/ Industrial Engineering

Category

Industrial Engineering

Industrial engineering formulas and calculators for operations research, quality control, and process optimization used to improve production efficiency. Includes queuing theory, inventory management, and SPC equations.

30Formulas
2Subcategories
Updated Jul 2026

General

SMED Setup Time Reduction Ratio

Reduction (%) = ((Old Setup Time - New Setup Time) / Old Setup Time) * 100

General

Total Float (Project Scheduling)

TF = Late Start - Early Start

General

Project Crash Cost per Day

Crash Cost/Day = (Crash Cost - Normal Cost) / (Normal Time - Crash Time)

General

Standard Time (With Allowances)

ST = Normal Time * (1 + Allowance Factor)

General

Learning Curve Time Reduction

T_n = T_1 * n^(log2(LR))

Quality Control

Failure Rate

λ = 1 / MTBF

Quality Control

System Availability (Reliability Engineering)

Availability (%) = (MTBF / (MTBF + MTTR)) * 100

Quality Control

Mean Time To Repair (MTTR)

MTTR = Total Repair Time / Number of Repairs

Quality Control

Mean Time Between Failures (MTBF)

MTBF = Total Operating Time / Number of Failures

Quality Control

Rolled Throughput Yield

RTY = Y1 * Y2 * Y3 * ... * Yn

Quality Control

First Pass Yield

FPY (%) = (Units Passing Without Rework / Total Units Started) * 100

Quality Control

Process Capability Index (Cpk, Accounting for Centering)

Cpk = min[(USL - μ)/(3σ), (μ - LSL)/(3σ)]

Quality Control

X-bar Control Chart Limits

UCL/LCL = X̄̄ ± A2 * R̄

Quality Control

Defects Per Million Opportunities (DPMO)

DPMO = (Number of Defects / (Units * Opportunities per Unit)) * 1,000,000

Quality Control

Six Sigma Process Sigma Level

Sigma Level ≈ 0.8406 + sqrt(29.37 - 2.221*ln(DPMO))

Operations Research

Inventory Turnover Ratio (Manufacturing)

Turnover = Cost of Goods Sold / Average Inventory Value

Operations Research

Production Throughput Rate

Throughput = Units Produced / Time Period

Operations Research

Assembly Line Balancing Efficiency

Efficiency (%) = (Sum of Task Times / (Number of Stations * Cycle Time)) * 100

Operations Research

Manufacturing Cycle Time

Cycle Time = Total Production Time / Units Produced

Operations Research

Takt Time

Takt Time = Available Production Time / Customer Demand

Operations Research

Average Wait Time in System (M/M/1)

W = 1 / (μ - λ)

Operations Research

Average Number in Queue (M/M/1)

Lq = ρ² / (1 - ρ)

Operations Research

Traffic Intensity (M/M/1 Queue Utilization)

ρ = λ / μ

Operations Research

Newsvendor Critical Ratio

CR = Cu / (Cu + Co)

Operations Research

Safety Stock (Variable Demand and Lead Time)

SS = Z * sqrt(LT * σd² + d² * σLT²)

Operations Research

Reorder Point

ROP = (Average Daily Demand * Lead Time) + Safety Stock

Quality Control

Overall Equipment Effectiveness

OEE = Availability × Performance × Quality

Quality Control

Process Capability Index

C_p = (USL − LSL) / (6σ)

Operations Research

Little's Law

L = λW

Operations Research

Economic Order Quantity

EOQ = √(2DS / H)